Pembangunan Waduk Rawa Badung Capai 90 Persen

Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. Water Channel on Jalan SPG 7 Being Improved

    access_time18-09-2026 remove_red_eye836 personNurito
  2. Jakarta Pushes to Strengthen Food Ecosystem

    access_time18-09-2026 remove_red_eye614 personAldi Geri Lumban Tobing
  3. Pramono Departs for New York to Discuss Climate and Food Crises

    access_time18-09-2026 remove_red_eye581 personDessy Suciati
  4. Operations of the MV Doulos Hope Ship Library Delayed

    access_time18-09-2026 remove_red_eye562 personAnita Karyati
  5. Sumenep Park Revitalization to Be Aligned with Gresik River Flow

    access_time18-09-2026 remove_red_eye463 personFolmer